During PI Planning’s management review and problem solving meeting, the System Architect notices that an Enabler to build an API is planned to be delivered in the same Iteration as a Feature requiring the API.
What action should the System Architect take?
A . Wait until the end of PI Planning and ROAM the risk
B . Vote "one" during the PI confidence vote to highlight the risk
C . Work with Product Management and teams to resolve the risk during team breakouts
D . Tell one of the teams to adjust their plans so there are no dependencies across teams in the same
iteration
Answer: C
Explanation:
Work with Product Management and teams to resolve the risk during team breakouts