What action should the program manager take first?

A program with objectives that impact a large segment of the population receives negative commentary from organizations representing the public interest.

What action should the program manager take first?
A . Rework the stakeholder engagement plan to foster better relationships with the affected stakeholder groups.
B . Review the stakeholder register to determine the ability of the affected stakeholder group(s) to affect program outcomes.
C . Assess the risk of sustained negative media coverage.
D . Discuss the issues with the governance board to determine next steps.

Answer: A