What action should be taken on Relentless Improvement Backlog items from the Problem Solving Workshop?
A . Assign points or prioritization levels
B. Calculate for cost before continuing
C. Use as direct input into the PI Planning session that follows
D. Assign to the team best suited to solve
Answer: C
Explanation:
https://www.scaledagileframework.com/inspect-and-adapt/
Latest SSM Dumps Valid Version with 204 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund