Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
A . Activate availability control For projects in the control area. Enter the plan data for each WBS element.
B. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.
C. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.
D. management in the project definition. Enter the budget in the master data of the top WBS element.
E. Activate commitment
Answer: C