Which material would have the largest contribution to Materials and Resources Credit, Building Product Disclosure and Optimization- Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?
- A . 75% Rainforest Alliance Certified flooring with a total cost of $3,000 USD
- B . 10% Rainforest Alliance Certified furniture with a total cost of $30,000 USD
- C . 50% Rainforest Alliance Certified wood veneer with a total cost of $5,000 USD
- D . 100% Rainforest Alliance Certified wheatboard with a total cost of $2,000 USD
A project team is pursuing certification for a medical clinic with 150 full time employees and 250 peak visitors. The project team is considering the Location and Transportation Credit for Bicycle Facilities. Providing which of the following is a minimum requirement to earn the credit?
- A . A bicycle maintenance program for employees
- B . At least one on-site shower and changing facility for employees
- C . Seven short-term bicycle storage spaces within 50 ft. (15 m) of the project’s main entrance
- D . Six long-term bicycle parking spaces within 50 ft. (15 m) of the project’s main entrance
A project has performed an energy model which has resulted in the following energy end use consumption:
To meet the requirements for Energy and Atmosphere Credit, Advanced Energy Metering, Option 2. Advanced Metering, energy meters must be installed for energy end uses in
- A . space cooling, interior fans and receptacles
- B . interior lighting, space heating, space cooling and interior fans
- C . interior lighting, space heating, space cooling, interior fans and receptacles
- D . exterior lighting, interior lighting, space heating, space cooling, interior fans, service water heating and receptacles
A luxury hotel project is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies.
Which of the following credits would be applicable?
- A . Regional Priority Credit, Optimize Energy Performance
- B . Indoor Environmental Quality Credit, Quality Views, Exemplary Performance
- C . Indoor Environmental Quality Credit, Acoustic Performance, Exemplary Performance
- D . Energy and Atmosphere Credit, Enhanced Commissioning, Exemplary Performance
A project team wants to achieve Materials and Resources Credit, Building Product Disclosure and Optimization – Material Ingredients.
By what means can a product demonstrate their material ingredient optimization?
- A . Green Seal
- B . Manufacturer Inventory
- C . GreenScreen v1.2 Benchmark
- D . Chemical Abstract Service Registration Number (CASRN)
A renovation project includes both a new kitchen sink and shower and an existing lavatory and water closet within the LEED project boundary.
How would the project perform the Water Efficiency Credit, Indoor Water Use Reduction calculations?
- A . Include only the newly installed fixtures and exclude the existing fixtures
- B . Include only the existing fixtures and exclude the newly installed fixtures
- C . Include all fixtures (new and existing); the baseline for the existing fixtures would be the flush/flow rates of the existing fixtures prior to retrofit
- D . Include all fixtures (new and existing); the baseline for the existing fixtures would be the same baseline flush/flow rates used for the new fixtures
A project team chooses to pursue the Integrative Process Credit.
Which of the following credits can be affected by early planning? (Choose One Answer only)
- A . Location and Transportation Credit, Access to Quality Transit
- B . Energy and Atmosphere Credit, Green Power and Carbon Offsets
- C . Indoor Environmental Quality Credit, Indoor Air Quality Assessment
- D . Energy and Atmosphere Credit, Advance Energy Metering
Which of the following information is needed to document the non-structural elements that will be reused from the existing space in a LEED AP Interior Design and Construction project?
- A . Elevations and space plans
- B . A tracking spreadsheet and cut sheets
- C . Cut sheets and drawings indicating elements to be reused
- D . Drawings indicating elements to be reused and a tracking spreadsheet
When developing the overall energy strategy of the project, which credit should the client consider to work synergistically with the Energy and Atmosphere Credit, Enhanced Commissioning, on an ongoing basis?
- A . Advanced Energy Metering
- B . Renewable Energy Production
- C . Green Power and Carbon Offsets
- D . Enhanced Refrigerant Management
A tenant is soliciting proposals for a Commissioning (Cx) agent for Energy and Atmosphere Credit, Enhanced Commissioning.
Which qualification must the agent meet?
- A . Subcontractor of construction manager
- B . Not an employee of the project design firm
- C . Member of the Building Cx Association
- D . Commissioning Authority (CxA) with experience in at least one prior project