A project has access to two alternative water sources.
How should they determine which source to use where?
- A . A project may not use two alternative water sources
- B . Target the uses that require the least treatment first, such as toilet flushing or irrigation
- C . Match uses by location: indoor sources to indoor uses, outdoor sources to outdoor uses
- D . All sources should be treated to potable water standards and used to supplement the municipal supply
Source reduction appears at the top of the Environmental Protection Agency’s (EPA’s) hierarchy because it
- A . reduces environmental impacts by reusing existing materials
- B . reduces environmental impacts associated with material containing high levels of toxic chemicals
- C . reduces environmental impacts throughout the material’s life cycle by specifying recycled content in the material selected
- D . reduces environmental impacts throughout the material’s life cycle, from the supply chain and use to recycling and waste disposal
An owner has expressed concerns to the LEED AP about the costs associated with the integrative process.
How can the LEED AP relieve the owner’s concerns?
- A . The LEED AP should explain to the owner that since the integrative process is not a prerequisite, it can be dropped from the project thus cutting back project costs
- B . The LEED AP should explain that while the first costs and the design fees will be higher due to the integrative
process, the operational savings will make up for the extra costs - C . The LEED AP should explain that the integrative process can easily be postponed and reconsidered until after
the design for the construction phase, when it will most likely save costs for the project - D . The LEED AP should explain that the integrative process reduces costs by avoiding delays associated with design changes during the construction document phase and reducing change orders during construction
To satisfy the Increased Ventilation strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies, the breathing zone rates of outdoor air ventilation to all occupied spaces must be increased above the minimum rates required in ASHRAE 62.1-2010 by at least what percentage?
- A . 10%
- B . 20%
- C . 30%
- D . 50%
Which of the following phases should be included in the Integrative Process Credit, Integrative Process in order to comply with the intent of this credit?
- A . Discovery; design and construction; occupancy; operations and feedback
- B . Discovery and design; construction and occupancy; post occupancy and operations
- C . Pre-design and design; construction and occupancy; post occupancy and operations
- D . Pre-design and design; construction and pre-occupancy; post occupancy and operations
A tenant implements the following strategies to reduce the amount of water used.
Which strategy is applicable to the Water Efficiency Credit, Indoor Water Use Reduction for LEED Interior Design and Construction: Commercial Interiors?
- A . Composting toilet
- B . Low-flow irrigation system
- C . Commercial clothes washer
- D . Roof runoff for chiller make-up water
Which of the following must be considered in order to meet Energy and Atmosphere Prerequisite, Fundamental Refrigerant Management if the tenant requires 24-hour cooling in a server room?
- A . Base-building chiller specifications
- B . CFC-free refrigerants in tenant cooling units
- C . Temperature monitoring of building cooling water
- D . ENERGY STAR® compliant cooling units with low CFCs
A tenant with 1,000 employees wishes to pursue LEED Interior Design and Construction Certification for their space in which they will be the sole tenant.
Which of the following building attributes will help the tenant achieve points in the Location and Transportation category?
- A . A car sharing program
- B . 60 bike racks and seven shower/changing rooms
- C . Electric car charging stations in the parking garage
- D . A bus line with 30 daily rides with a bus stop within 1/2 mi. (0.80 km) of the building entrance
If the client has purchased green power that is not Green-e certified, then the project team should
- A . accept not earning Energy and Atmosphere Credit, Green Power
- B . provide documentation as to how the green power is equivalent to Green-e certified
- C . apply for an Innovation Credit and explain the situation in a narrative
- D . apply the percentage to Energy and Atmosphere Credit, Renewable Energy Generation
Discussing the project goals to help identify the credits and options that the team should attempt is an example of
- A . documenting LEED credits
- B . creating the Basis of Design
- C . developing the LEED Scorecard
- D . implementing the Commissioning Plan