True or False: Scrum Events, Scrum Team Accountabilities, and Scrum Artifacts are augmented when using Scrum with Kanban. For example, having a clear indicator of the age of active Sprint Backlog items may help the Scrum Team during the Daily Scrum, helping them to better Inspect and Adapt their daily work.
A . True
B. False
Answer: A
Explanation:
Adding Kanban to Scrum provides a technique to help the Scrum Team focus on driving a continuous flow of activity but does not negate value provided by the Scrum Events, Scrum Artifacts, and Scrum Team Accountabilities. However, flow-based metrics/charts & forecasts may get added to Scrum Events as per the Kanban Guide for Scrum Teams.