Exam4Training

True or False: If Developers use tasks, then their WIP limits should primarily apply to tasks in the Sprint Backlog.

True or False: If Developers use tasks, then their WIP limits should primarily apply to tasks in the Sprint Backlog.
A . True
B. False

Answer: B

Explanation:

Limiting tasks in progress can be useful but does not replace limiting WIP at the PBI level. We care about flow of value/learning. This is the flow of PBIs.

Latest PSK-I Dumps Valid Version with 350 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version