True or False: All Scrum Team members must attend the Nexus Daily Scrum.

True or False: All Scrum Team members must attend the Nexus Daily Scrum.
A . True
B . False

Answer: B

Explanation:

The answer is false because not all Scrum Team members are required to attend the Nexus Daily Scrum. According to the Online Nexus Guide1, the Nexus Daily Scrum is an event for appropriate representatives from individual Scrum Teams to inspect the current state of the Integrated Increment and to identify integration issues or newly discovered cross-team dependencies. The appropriate representatives are those who can best collaborate and communicate the progress and impediments of their Scrum Teams, and who can make and influence decisions regarding the integration and delivery of the product. The number and selection of the representatives may vary depending on the context and needs of the Nexus 234. The Nexus Daily Scrum does not replace the Daily Scrum of each Scrum Team, which is still held by all the Developers of the team to plan their work for the day 5.

Latest SPS Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version