Exam4Training

To which team should the error-correction activity be transferred?

The incident management team is unable to determine the root cause of an incident.

To which team should the error-correction activity be transferred?
A . Performance Management
B . Change Management
C . Availability Management
D . Problem Management

Answer: D

Exit mobile version