To what should the project manager refer to implement this suggestion?
A team member suggests using a mobile instant messaging application to allow the team
to promptly approve measures for improving the project’s schedule and costs.
To what should the project manager refer to implement this suggestion?
A . Stakeholder engagement plan
B . Schedule baseline
C . Change management plan
D . Scope management plan
Answer: A