To what should the project manager refer?
A protects outcome is highly sensitive to and dependent upon financial market activity Therefore, the company’s financial advisor delivers daily exchange rate forecasts. The projects budget was planned using a conservative scenario with high exchange-rate variations. The project manager now wants to review this budget to update the probability and impact of a possible new scenario using current financial conditions
To what should the project manager refer?
A . Stakeholder register
B . Risk register
C . Lessons learned
D . Marketplace conditions
Answer: D