To support the work, what should the project manager do next?
An IT department’s deliverable is two weeks late If the deliverable is not completed by the end of the week the project will be placed on hold Within the last two weeks the project manager communicated the issue to the IT department, spoke with the IT project manager and elevated the risk level in the risk register.
To support the work, what should the project manager do next?
A . Validate the communications management plan
B . Communicate to the project stakeholders that the project will be delayed
C . Analyze stakeholder communications requirements.
D . Apply the escalation process defined in the communications management plan.
Answer: D