To increase the likelihood of the success of a software project, the project plan should meet which of the following requirements?
To increase the likelihood of the success of a software project, the project plan should meet which of the following requirements?
A . It should be completed before the project activities begin.
B . It should be reviewed and updated at each phase of the project.
C . It should be developed by an independent software developer
D . It should be approved by the steering committee.
Answer: B
Explanation:
Dynamic Planning: A project plan that is reviewed and updated at each phase ensures that it remains relevant and accurate, reflecting any changes in scope, resources, or timelines. Continuous Improvement: Regular updates allow for continuous improvement and alignment with project goals and stakeholder expectations.
Standards and Guidelines: Project management standards, such as those outlined by the Project Management Institute (PMI), advocate for iterative review and updating of project plans.
Latest CSQE Dumps Valid Version with 173 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund