Through which process does the implementation of new or changed services, including closure of a service, need to be planned and approved?

Through which process does the implementation of new or changed services, including closure of a service, need to be planned and approved?
A . Business Relationship Management
B. Change Management
C. Release Management
D. Service Level Management

Answer: B