This type of analysis is an example of which of the following?

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.

This type of analysis is an example of which of the following?
A . Cost performance index
B . Risk mitigation
C . Schedule variance
D . Cost variance

Answer: C