When using a change-driven approach, the business analyst may create an initial list of high-level requirements for the initiative.
This high-level requirements list is also known as what term?
A . Requirements envisioning
B . Project scope
C . Product scope
D . Requirements foundation
Answer: A
Explanation:
The initial high-level listing of requirements in a change-driven approach is also known as requirements envisioning.
Answer. B is incorrect. Project scope defines all of the required work to satisfy the requirements of the project.
Answer. C is incorrect. Product scope defines all of the features and functions of the thing, solution, or service the project or organization will create.
Answer. D is incorrect. Requirements foundation is not a valid term for business analysis.