The variable overhead efficiency variance is:

The variable overhead efficiency variance is:
A . The same as the direct labour efficiency variance
B . The difference between the actual hours worked and the standard hours produced, multiplied by the variable overhead absorption rate
C . The difference between the actual variable overheads incurred and those absorbed
D . The actual hours worked multiplied by the variable overhead absorption rate

Answer: B