The team’s draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)
A . Capacity and load estimates (Correct)
B. Program delivery schedule
C. Draft PI Objectives
D. Risks and impediments
E. Iteration Goals
F. Refined team backlogs
Answer: A,C,D