The team’s draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)
A . Capacity and load estimates (Correct)
B . Program delivery schedule
C . Draft PI Objectives
D . Risks and impediments
E . Iteration Goals
F . Refined team backlogs
Answer: A,C,D
Latest SAFe-RTE Dumps Valid Version with 120 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund