Exam4Training

The Sprint Goal and the Sprint Backlog are outputs from the Sprint Planning.

The Sprint Goal and the Sprint Backlog are outputs from the Sprint Planning.

True or False:
A . False
B . True

Answer: B

Latest PSPO-III Dumps Valid Version with 65 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version