Site icon Exam4Training

The ScrumMaster and the Product Owner disagree on the value of a Product Backlog item.

The ScrumMaster and the Product Owner disagree on the value of a Product Backlog item.

In order to resolve the disagreement, the first step the ScrumMaster should take is to ask:
A . The Product Owner to clarify the requirement.
B . The business owner to resolve the problem.
C . The business analyst to research the product value.
D . Another project manager how to resolve the problem.

Answer: A

Latest PMI-ACP Dumps Valid Version with 717 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version