The Scrum Master can decide which Scrum Events are required in the Scrum project.

The Scrum Master can decide which Scrum Events are required in the Scrum project.
A . False
B. True

Answer: A

Explanation:

Scrum defines which Events are required in all Scrum project, not the Scrum Master. It is always required to have the Sprint Planning, the Daily Scrums, the Sprint Review and the Sprint Retrospective in every project.