The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
A . exploit
B . avoid
C . mitigate
D . share

Answer: C