The remediation plan should be evaluated at what point in the change lifecycle?
The remediation plan should be evaluated at what point in the change lifecycle?
A . Before the change is approved
B . Immediately after the change has failed and needs to be backed out
C . After implementation but before the post implementation review
D . After the post implementation review has identified a problem with the change
Answer: A