Examine the following Business Object Action diagram:
The purpose of the Action is to process new orders through the order processing system. Order details of provided to the Action by the Process and stored in the ‘Order Data’ Collection According to Blue Prism best practices, what is wrong with this Action?
A . A Single Row Collection cannot receive data from a Process
B . A Wait stage is missing between the ‘Click Submit’ stage and the ‘End’ stage
C . A Wait stage is missing between the ‘Start’ stage and the ‘Write Order Details’ stage
D . An Action description has not been provided
E . A Wait stage is missing after the ‘Write Order Details’ stage
Answer: E
Explanation:
A Wait stage is needed after the ‘Write Order Details’ stage to ensure that the application has time to process the order details before clicking the Submit button. Without a Wait stage, the automation may fail due to timing issues.
Reference: https://portal.blueprism.com/sites/default/files/2021-05/Blue%20Prism%20Certification%20-%20Associate%20Developer%20-%20Certification%20Overview_0.pdf (page 11)