The purpose of developing a project scope management plan is to:

The purpose of developing a project scope management plan is to:
A . Manage the timely completion of the project.
B . Ensure that the project includes all of the work required.
C . Make sure the project will satisfy the needs for which it was begun.
D . Reduce the risk of negative events in the project.

Answer: B