The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?
The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way.
The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?
A . Product owner
B . Change control board (CCB)
C . Project sponsor
D . Project manager
Answer: D