The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success.

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success.

The engagement level of the stakeholders should be classified as:
A . Supportive
B . Leading
C . Neutral
D . Resistant

Answer: B