The Product Owner has the final say on if an Increment is Done. Choose the best answer
A . True
B. False
Answer: B
Explanation:
All Scrum Team is responsible. If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product.