The Product Backlog is baselined before the Sprint 0.
The Product Backlog is baselined before the Sprint 0.
A . False
B. True
Answer: A
Explanation:
This statement is wrong because the Product Backlog is not baselined (fixed) and there is no Sprint 0 in Scrum.