The Product Backlog: (choose the best two answers)

The Product Backlog: (choose the best two answers)
A . only contains items defined by the Product Owner.
B. is visible to the Scrum Team and stakeholders.
C. is ordered by the Product Owner.
D. is managed by the Scrum Master.
E. must be finalized before the first Sprint can start.
F. is only described through User Stories.

Answer: B,C

Explanation:

The Product Owner is responsible for the content, availability, and ordering of the Product Backlog. The initial creation of the Product Backlog is lays out the initially known and best-understood requirements and evolves as the product and the environment in which it will be used evolves. It constantly changes to identify what the product needs to be appropriate, competitive, and useful. Scrum relies on transparency and the perceived state of the artifacts in order to make product decisions. Incomplete transparency can result in flawed decision making, diminished value, and added risk.

Latest PSPO-II Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments