The process of prioritizing risks for further analysis or action is known as:

The process of prioritizing risks for further analysis or action is known as:
A . Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis.

Answer: C