The process of prioritizing risks for further analysis or action is known as:
The process of prioritizing risks for further analysis or action is known as:
A . Plan Risk Management.
B . Plan Risk Responses.
C . Perform Qualitative Risk Analysis.
D . Perform Quantitative Risk Analysis.
Answer: C