Exam4Training

The primary purpose of a milestone in a project is to show:

The primary purpose of a milestone in a project is to show:
A . significant events.
B . resource constraints.
C . task dependencies.
D . critical path highlights.

Answer: A

Latest APM-PFQ Dumps Valid Version with 354 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version