The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
A . Work packages.
B. Accepted deliverables.
C. The WBS dictionary.
D. The scope baseline.
Answer: A
Latest CAPM Dumps Valid Version with 1089 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund