The outsourcing of the dangerous work to a specialist is what type of risk response?
You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you’ve decided is too risky for the program team members so you’ve hired specialists to manage the dangerous work .
The outsourcing of the dangerous work to a specialist is what type of risk response?
A . Avoidance
B . Mitigation
C . Transference
D . Enhancing
Answer: C