Which approach to model, measure, and analyze business value is primarily concerned with identifying the participants involved in creating and delivering value?

Which approach to model, measure, and analyze business value is primarily concerned with identifying the participants involved in creating and delivering value?A . Value chainsB . Value networksC . Lean value streamsD . Value streamsView AnswerAnswer: B Explanation: Value networks are an approach to model, measure, and analyze business value...

September 21, 2024No CommentsREAD MORE +

Why would such Architecture Descriptions need to be updated in Phase B?

Consider the following: In Phase A a business capability map and a core set of value streams were created while developing the Architecture Vision. Why would such Architecture Descriptions need to be updated in Phase B?A . Phase B requires that all Architecture Descriptions be updated.B . The development of...

September 20, 2024No CommentsREAD MORE +

Which ADM Phase(s) does this describe?

Refer to the table below: Which ADM Phase(s) does this describe?A . Preliminary PhaseB . Phase BC . PhaseD . C and DE . Phase EView AnswerAnswer: C Explanation: The table describes the steps involved in Phase B (Business Architecture), Phase C (Information Systems Architectures), and Phase D (Technology Architecture)...

September 20, 2024No CommentsREAD MORE +

Which statement is correct in this scenario?

You built a number of DLP profiles for different sensitive data types. If a file contains any of this sensitive data, you want to take the most restrictive policy action but also create incident details for all matching profiles. Which statement is correct in this scenario?A . Create a Real-time...

September 18, 2024No CommentsREAD MORE +

What is defined as the effect of uncertainty on objectives?

What is defined as the effect of uncertainty on objectives?A . ThreatB . ContinuityC . RiskD . VulnerabilityView AnswerAnswer: C Explanation: Risk is defined as the effect of uncertainty on objectives. It can be positive or negative depending on whether it enhances or hinders the achievement of objectives. Threat is...

September 15, 2024No CommentsREAD MORE +

In what TOGAF ADM phase is the information map linked to other business blueprints?

In what TOGAF ADM phase is the information map linked to other business blueprints?A . Phase BB . Phase EC . Phase AD . Preliminary PhaseView AnswerAnswer: B Explanation: Phase E Explanation of Correct Answer. In Phase E (Opportunities and Solutions) of the TOGAF Explanation ADM, the information map is...

September 15, 2024No CommentsREAD MORE +

Which of the following describes how business models are used within the TOGAF standard?

Which of the following describes how business models are used within the TOGAF standard?A . To identify, classify, and mitigate risks to the business.B . To tailor the enterprise architecture for the business.C . To document the factors impacting the business migration plan.D . To help formulate architecture and business...

September 14, 2024No CommentsREAD MORE +

Which of the following best describes the relationship between business models and business architecture?

Which of the following best describes the relationship between business models and business architecture?A . Business Architecture provides a conceptual summary view, whereas business models support in-depth analysis.B . Business Architecture breaks a business model down into the core functional elements that describe how the business works.C . Business models...

September 12, 2024No CommentsREAD MORE +

Which of the following is a difference between an organization map and an organization chart?

Which of the following is a difference between an organization map and an organization chart?A . An organization map highlights where in the organization that stakeholder concerns are not being addressed by a business architecture.B . An organization map can be impacted by a business model change.C . An organization...

September 12, 2024No CommentsREAD MORE +