Consider the following ADM phases objectives.
Objective
1-Determine whether an incremental approach is required, and if so identify Transition Architectures that will deliver continuous business value
2-Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D
3-Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan
4-Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders
Which phase does each objective match?
- A . 1E-2F-3E-4F
- B . 1G-2E-3F-4F
- C . 1E-2E-3F-4F
- D . 1F-2E-3F-4G
Complete the sentence The purpose of Enterprise Architecture is to_______________.
- A . take major improvement decisions
- B . control the bigger changes
- C . guide effective change
- D . govern the stakeholders
What can architects present to stakeholders to extract hidden agendas, principles, and requirements that could impact the final Target Architecture?
- A . Solutions and Applications
- B . Alternatives and Trade-offs
- C . Business Scenarios and Business Models
- D . Architecture Views and Architecture Viewpoints
What is an objective of the ADM Implementation Governance Phase?
- A . To provide continual monitoring of the governance framework
- B . To ensure conformance for the target architecture
- C . To finalize the Implementation and Migration Plan
- D . To establish the resources for architecture governance
Which section of the TOGAF template for Architecture Principles should highlight the requirements for carrying out the principle?
- A . Rationale
- B . Name
- C . Statement
- D . Implications
Complete the sentence The Enterprise Continuum provides methods for classifying architecture artifacts as they evolve from________________________.
- A . Solutions Architectures to Solution Building Blocks
- B . generic architectures to reusable Solution Building Blocks
- C . Foundation Architectures to re-usable architecture assets
- D . generic architectures to Organization-Specific Architectures
Complete the sentence The Architecture Landscape is divided into levels known as__________________________.
- A . Gaps Plateaus, and Target Architectures
- B . Baseline. Transition and To Be Architectures
- C . Segment Strategic and Capability Architectures
- D . Transitional Complete and incremental Architectures
In which phase of the ADM cycle do building blocks become implementation-specific?
- A . Phase B
- B . Phase C
- C . Phase D