The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
A . Planned date of the next call, independent of maintenance order dates
B . Actual finish date of the maintenance order
C . The date of the final confirmation
D . Technical completion date of the maintenance order
Answer: C
Explanation:
When dealing with a maintenance strategy plan in SAP where shift factors are set to 100%, and there’s a delay in maintenance work, the relevant date for recalculating future planned dates is crucial to ensure that the scheduling remains accurate. Here is the correct option based on this setup:
The date of the final confirmation – Correct. In the context of maintenance planning where shift factors are at 100%, the date of the final confirmation becomes crucial. This date indicates when the work was actually confirmed as completed, which is important because with a shift factor of 100%, any delay or advance in the maintenance schedule directly impacts the subsequent maintenance cycles. The system uses this date to adjust and recalibrate the next planned dates, ensuring that maintenance cycles reflect the actual conditions and timings of completed work.
Latest C_S43_2022 Dumps Valid Version with 80 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund