The main outcome of risk identification, in a risk management process, is to:
A . identify and determine the relative importance of the project risks.
B . identify and describe all risks that might occur on the project.
C . identify and determine the responses to the project risks.
D . identify and describe risks that have occurred on previous projects
Answer: B
Latest APM-PFQ Dumps Valid Version with 354 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund