the following tools should the project manager adopt first to help track and prioritize a resolution?
During quality analysis, different team members are identifying multiple constraints.
Which of
the following tools should the project manager adopt first to help track and prioritize a resolution?
A . Issue log
B . Defect log
C . Risk register
D . Change log
Answer: A
Explanation:
An issue log is a tool that records and tracks any issues that arise during the project. It helps the project manager to identify, prioritize, assign, monitor, and resolve the issues in a timely manner. An issue log can also include information such as the issue description, impact, status, owner, and resolution date1. An issue log is different from a defect log, which records and tracks the defects or errors in the project deliverables. A risk register is a tool that records and tracks the potential risks that may affect the project objectives. A change log is a tool that records and tracks the changes that are made to the project scope, schedule, budget, or quality2.
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund