The following are essential factors when estimating the Portfolio Epic duration: (Choose three)

The following are essential factors when estimating the Portfolio Epic duration: (Choose three)
A . Related Development Values Stream Canvas
B. Capacity allocation for each of the assigned ARTS
C. Historical Velocity of Assigned ARTS
D. Related ART Canvas
E. Epic Size in Story points for each ART
F. PI Roadmap

Answer: B,C,E