The "Definition of Ready" shows the team when Product Backlog items are ready to be selected for the Sprint Backlog.

The "Definition of Ready" shows the team when Product Backlog items are ready to be selected for the Sprint Backlog.
A . False
B. True

Answer: A

Explanation:

There is no concept of a "Definition of Ready" in Scrum. Of course it is recommended to refine the items on the top of the Product Backlog as good as possible, but items can always be selected (also unrefined ones) and be refined during the sprint.