The Definition of Ready is defined by the Product Owner.
The Definition of Ready is defined by the Product Owner.
A . False
B. True
Answer: A
Explanation:
The concept of a Definition of Ready is not accepted by Scrum.
Latest PSPO-I Dumps Valid Version with 481 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments