The company has received an HPC (High-Performance Computing) project, and Engineer A needs to select the products in the best order. Which is the correct sequence?
The company has received an HPC (High-Performance Computing) project, and Engineer A needs to select the products in the best order. Which is the correct sequence?
① Determine the overall computing capability based on research requirements;
② Select compute nodes, fat nodes, and acceleration node devices;
③ Determine OS and application software selection;
④ Determine storage devices and parallel file systems;
⑤ Determine network type and network devices.
A . ③①④②⑤
B. ③①②④⑤
C. ①②③④⑤
Answer: B