The company has received an HPC (High-Performance Computing) project, and Engineer A needs to select the products in the best order. Which is the correct sequence?

The company has received an HPC (High-Performance Computing) project, and Engineer A needs to select the products in the best order. Which is the correct sequence?

① Determine the overall computing capability based on research requirements;

② Select compute nodes, fat nodes, and acceleration node devices;

③ Determine OS and application software selection;

④ Determine storage devices and parallel file systems;

⑤ Determine network type and network devices.
A . ③①④②⑤
B. ③①②④⑤
C. ①②③④⑤

Answer: B