The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
A . Only 1 is true
B . Only 2 is true
C . Both 1 and 2 are true
D . Neither 1 or 2 are true
Answer: B
Explanation:
The statement that "The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved" is true. This process is crucial for ensuring that the project has met its objectives and that all remaining project deliverables are acceptable to stakeholders. The first statement is incorrect as the receipt of completed Work Packages is typically handled during the ‘Managing a Stage Boundary’ process rather than in the ‘Closing a Project’ process.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources