The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
A . Project management plan.
B. Project charter.
C. Work breakdown structure.
D. Stakeholder register.
Answer: B
Latest CAPM Dumps Valid Version with 1089 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments