The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
A . Project management plan.
B. Project charter.
C. Work breakdown structure.
D. Stakeholder register.

Answer: B