The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
A . Project management plan.
B . Project charter.
C . Work breakdown structure.
D . Stakeholder register.
Answer: B