The basic metrics of flow that Scrum Teams using Kanban will need to track are: (choose the four best answers)

The basic metrics of flow that Scrum Teams using Kanban will need to track are: (choose the four best answers)
A . Lead Time
B. Velocity
C. Work in Progress (WIP)
D. Cycle Time
E. Throughput
F. Work Item Age

Answer: C,D,E,F

Explanation:

The four basic metrics of flow that Scrum Teams using Kanban need to track are as follows:

Work in Progress (WIP): The number of work items started but not finished.

Cycle Time: The amount of elapsed time between when a work item starts and when a work item finishes.

Work Item Age: The amount of time between when a work item started and the current time. This applies only to items that are still in progress.

Throughput: The number of work items finished per unit of time.