The basic metrics of flow that Scrum Teams using Kanban will need to track are: (choose the four best answers)
The basic metrics of flow that Scrum Teams using Kanban will need to track are: (choose the four best answers)
A . Lead Time
B. Velocity
C. Work in Progress (WIP)
D. Cycle Time
E. Throughput
F. Work Item Age
Answer: C,D,E,F
Explanation:
The four basic metrics of flow that Scrum Teams using Kanban need to track are as follows:
Work in Progress (WIP): The number of work items started but not finished.
Cycle Time: The amount of elapsed time between when a work item starts and when a work item finishes.
Work Item Age: The amount of time between when a work item started and the current time. This applies only to items that are still in progress.
Throughput: The number of work items finished per unit of time.
Latest PSK-I Dumps Valid Version with 350 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund